Work Performed this Week:

  • Continued interior CMU and brick in Units A and C
  • Continued non-load bearing interior CMU walls throughout
  • Continued exterior framing and sheathing in Unit A
  • Installed exterior composite wall panels and flashings in Units A, B, and C
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A and B
  • Continued priming and painting in Units B and C
  • Set ceramic tile in the locker rooms
  • Continued final hydronic and duct connections to the VAVs throughout
  • Continued hanging variable air volume (VAV) boxes and ductwork in Units A, C, and D
  • Hung duct in Food Service
  • Continued insulating low and medium pressure ductwork and hydronic pipe in Units A and B
  • Continued setting and welding steel hydronic piping in Unit C mechanical room
  • Installed lights in the ceiling grid in Units AB3 and AB2
  • Installed occupancy sensors in Units A and B
  • Pulled fire alarm wiring in Units A and B
  • Continued electrical rough-in in the mechanical room and gymnasium
  • Continued installing ceiling grid in Units AB2 and B1
  • Completed underground rough-in for the fuel pump
  • Set the new transformer and terminated conductor in the switchgear and new transformer
  • Set the electrical meter
  • Outage effecting the Central Office is scheduled between 5:00 am and 6:30 am on Monday, April 9, 2018 to make the final connection at the existing transformer and energize the new building
  • Set the gas meter

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.