5/21/2018 – Construction Update

Work Performed this Week:

  • Continued exterior framing at the entrance canopies 
  • Continued exterior masonry at the mechanical yard walls 
  • Continued hanging exterior metal panels in Unit B 
  • Continued work on the curtainwalls in Unit B 
  • Continued setting exterior frames, doors, and hardware 
  • Continued interior wall and ceiling framing, gypsum board, and finishing in Units A1, C, and D 
  • Continued ceiling grid in Unit D music 
  • Continued mechanical ductwork in Units A1, C, and D 
  • Continued mechanical pipe in the mechanical room and yard 
  • Continued flushing and filtering the mechanical pipe in preparation for equipment startup 
  • Continued work by all trades in the science classrooms in Units B3 and B2 
  • Continued terminating devices in Units AB3 and AB2 
  • Continued installing lights in AB1 
  • Continued pulling wire in Unit A1 
  • Continued terminating wiring in the main electric room and mechanical room 
  • Continued terminating control wiring in the main mechanical room and rooftop units 
  • The moisture level of the concrete substrate was tested for installation of the flooring systems 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

5/14/2018 – Construction Update

Work Performed this Week:

  • Completed South canopy structural steel 
  • Poured the entrance pad at the South canopy 
  • Continued pointing and patching CMU walls 
  • Continued framing walls, hanging gypsum board, and finishing walls in Unit A1, C, and D 
  • Continued exterior framing at the main entrance canopy 
  • Set exterior door frames 
  • Continued installing exterior composite wall panels in Unit B 
  • Installed pressure bars on the curtainwall in Unit B to permanent secure the glazing 
  • Continued installing windows in Unit D 
  • Continued installing ceiling grid in Unit D music 
  • Installed sprinkler pipe in the fire pump room 
  • Continued flushing and filtering the heating pipe 
  • Started the boilers 
  • Continued welding the chilled water pipes in the mechanical room and yard 
  • Roughed-in walls in the science classrooms 
  • Continued ductwork in food services, Unit D, and Unit A1 
  • Continued pulling cable to the rooftop air handling units and in the mechanical room 
  • Continued trimming out devices in Units A and B 
  • Continued terminating conductor in the main electrical room 
  • Continued installing lights in Units A and B 
  • Continued pulling data cable and trimming out devices in Units A and B 
  • Continued pulling access control wiring to the secured doors in Unit AB1 

 Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

4/30/2018 – Construction Update

Work Performed this Week:

  • Installed structural steel at the South entrance canopy 
  • Continued interior CMU and brick in Units A and C 
  • Continued non-load bearing interior CMU walls throughout 
  • Continued exterior framing and sheathing in Unit A 
  • Installed exterior composite wall panels and flashings in Units A, B, and C 
  • Continued setting windows in Unit A 
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A, B, C, and D 
  • Continued priming and painting in Units B and C 
  • Continued ceramic tile in the food service areas 
  • Continued final hydronic and duct connections to the variable air volume VAVs throughout 
  • Continued hanging variable air volume (VAV) boxes and ductwork throughout 
  • Continued hanging duct in food service 
  • Continued insulating low and medium pressure ductwork and hydronic pipe throughout 
  • Installed flex duct, diffusers, and louvers 
  • Continued setting and welding steel hydronic piping in Unit C mechanical room 
  • Installed lights in the ceiling grid in Units AB3 and AB2 
  • Installed occupancy sensors and other devices in Units A and B 
  • Pulled fire alarm wiring in Units A and B 
  • Continued trimming out electrical work in Units AB3 and AB2 
  • Continued electrical rough-in in the mechanical room and gymnasium 
  • Continued installing ceiling grid in Units AB2 and B1 
  • Continued installing gymnasium equipment 
  • Continued pouring sidewalks in the East parking lot 
  • Poured the concrete pad at the bus fuel tank 
  • Continued pulling data wiring in Unit B1 
  • The generators were delivered and set on the equipment pads in the mechanical yard 
  • The projector screens were delivered 
  • Relocated the field office trailers for resuming site work 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.