Work Performed this Week:

  • Installed structural steel at the South entrance canopy 
  • Continued interior CMU and brick in Units A and C 
  • Continued non-load bearing interior CMU walls throughout 
  • Continued exterior framing and sheathing in Unit A 
  • Installed exterior composite wall panels and flashings in Units A, B, and C 
  • Continued setting windows in Unit A 
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A, B, C, and D 
  • Continued priming and painting in Units B and C 
  • Continued ceramic tile in the food service areas 
  • Continued final hydronic and duct connections to the variable air volume VAVs throughout 
  • Continued hanging variable air volume (VAV) boxes and ductwork throughout 
  • Continued hanging duct in food service 
  • Continued insulating low and medium pressure ductwork and hydronic pipe throughout 
  • Installed flex duct, diffusers, and louvers 
  • Continued setting and welding steel hydronic piping in Unit C mechanical room 
  • Installed lights in the ceiling grid in Units AB3 and AB2 
  • Installed occupancy sensors and other devices in Units A and B 
  • Pulled fire alarm wiring in Units A and B 
  • Continued trimming out electrical work in Units AB3 and AB2 
  • Continued electrical rough-in in the mechanical room and gymnasium 
  • Continued installing ceiling grid in Units AB2 and B1 
  • Continued installing gymnasium equipment 
  • Continued pouring sidewalks in the East parking lot 
  • Poured the concrete pad at the bus fuel tank 
  • Continued pulling data wiring in Unit B1 
  • The generators were delivered and set on the equipment pads in the mechanical yard 
  • The projector screens were delivered 
  • Relocated the field office trailers for resuming site work 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.