5/14/2018 – Construction Update

Work Performed this Week:

  • Completed South canopy structural steel 
  • Poured the entrance pad at the South canopy 
  • Continued pointing and patching CMU walls 
  • Continued framing walls, hanging gypsum board, and finishing walls in Unit A1, C, and D 
  • Continued exterior framing at the main entrance canopy 
  • Set exterior door frames 
  • Continued installing exterior composite wall panels in Unit B 
  • Installed pressure bars on the curtainwall in Unit B to permanent secure the glazing 
  • Continued installing windows in Unit D 
  • Continued installing ceiling grid in Unit D music 
  • Installed sprinkler pipe in the fire pump room 
  • Continued flushing and filtering the heating pipe 
  • Started the boilers 
  • Continued welding the chilled water pipes in the mechanical room and yard 
  • Roughed-in walls in the science classrooms 
  • Continued ductwork in food services, Unit D, and Unit A1 
  • Continued pulling cable to the rooftop air handling units and in the mechanical room 
  • Continued trimming out devices in Units A and B 
  • Continued terminating conductor in the main electrical room 
  • Continued installing lights in Units A and B 
  • Continued pulling data cable and trimming out devices in Units A and B 
  • Continued pulling access control wiring to the secured doors in Unit AB1 

 Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.