Work Performed this Week:

  • Continued interior CMU pointing and patching 
  • Continued exterior metal sills and interior window trim 
  • Installed glass partition wall track in Unit B 
  • Glass partition panels delivered 
  • Installed operable partition wall track at the stage 
  • Continued hanging exterior composite metal panels in Units A, B, and C 
  • Continued framing interior walls, hanging gypsum board, and finishing in Units A, B, and C 
  • Continued ceiling grid and painting in Units C and D 
  • Interior wood wall panels delivered 
  • Began installing the terrazzo flooring in the commons areas 
  • Continued connecting food service equipment 
  • Continued installing ductwork and mechanical pipe in Units C and D 
  • Continued flushing and filtering the mechanical pipe and testing water quality 
  • Installed the split unit air conditioners in the IT closets 
  • IT closets were inspected for Owner acceptance with punch list distributed to the Contractor 
  • Installed equipment racks in the IT closets 
  • Continued pulling fire alarm wiring in Units C and D 
  • Continued terminating electrical devices in Units A, B, and C 
  • Continued terminating control wiring in the mechanical room and rooftop units 
  • Continued grading the ball field 
  • Removed construction security fencing 
  • Set the structural posts for the Cooley Field scoreboard 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.