7/16/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU pointing and patching 
  • Continued window framing and glazing in the research commons and main entrance 
  • Continued installing exterior composite metal panels along the radius wall 
  • Continued hanging and finishing gypsum board in administration and auditeria 
  • Painted the auditeria 
  • Dropped ceiling tile in Unit AB2 
  • Continued rubber floor tile in Unit AB3 and began in Unit AB2 
  • Continued polishing terrazzo flooring in the auditeria 
  • Continued hanging Marlite wood panels in Unit A 
  • Set operable glass partition walls in Units B3, B2, and B1 
  • Continued food service electrical connections 
  • Installed drinking fountains and restroom fixtures in Unit B3 
  • Continued installing ductwork at the stage 
  • Continued controls to the air handling units and programming the mechanical system 
  • Installed pulling data wiring in Units C and D 
  • Placed topsoil on the ball field 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.