Families enrolling students who are new to Williamsburg-James City County Public Schools should first check the school zone map to determine to which school their student is assigned. If your student is assigned to the new Blair Middle School, we invite you to register your child by visiting the JBMS main office.  Hours of registration […]

Fall Sports Information

Football – Head Coach, Dr. Mike Brown – There will be an informational football meeting Wednesday, August 1 at 5:30 p.m. in the Berkeley Middle School auditorium. The first practice is August 6 from 5:30-7 p.m. on Cooley Field. If you have questions, contact Coach Brown at dr.michael.brown76@gmail.com Volleyball – Head Coach, Jayme Phillips – Open Gym will […]

7/16/2018 – Construction Update

Work Performed this Week: Continued interior CMU pointing and patching  Continued window framing and glazing in the research commons and main entrance  Continued installing exterior composite metal panels along the radius wall  Continued hanging and finishing gypsum board in administration and auditeria  Painted the auditeria  Dropped ceiling tile in Unit AB2  Continued rubber floor tile […]

Cheerleading Tryout Information

The countdown is on: Only 64 days before James Blair Middle School opens its doors to students and staff! In the meantime, there are a whole lot of preparations going on. For example, cheer tryouts will be held on 8/23 and 8/24 from 4-5:30 p.m. Anyone wishing to try out must have a physical dated […]

6/25/2018 – Construction Update

Work Performed this Week: Continued interior CMU pointing and patching  Continued window framing and glazing in the research commons  Continued installing exterior composite metal panels  Continued hanging and finishing gypsum board in administration and auditeria  Applied final coat of paint in Unit AB3  Continued rubber floor tile in Unit AB3  Continued placing and polishing terrazzo […]

6/11/2018 – Construction Update

Work Performed this Week: Continued interior CMU pointing and patching  Continued exterior metal sills and interior window trim  Installed glass partition wall track in Unit B  Glass partition panels delivered  Installed operable partition wall track at the stage  Continued hanging exterior composite metal panels in Units A, B, and C  Continued framing interior walls, hanging […]