June 7, 2016 – 4th Middle School Update

At their June 7, 2016, Work Session an update on the JBMS project was presented to the WJCC School Board by Howard Collins, president of architectural firm Waller, Todd & Sadler, and Michael Hall, president and educational facility planner at Fanning Howey.

Mr. Collins said the project was on schedule to follow the below timeline:

Phase 1a (parking lot & new entrance for Central Office) May – August 2016
Phase 1b (JBMS design & construction) May 2016 – September 2018
Pre-final Design Documents (90%) May 20, 2016
Owner Review May 23 – June 6, 2016
Final Design Documents (100%) June 15, 2016
Permit Review June 15 – July 15, 2016
Bid Phase July 1 – August 4, 2016
Award August 16, 2016
Construction September 2016 – June 2018
Open September 2018

April 19, 2016 – 4th Middle School Update

At their April 19, 2016, Regular Meeting the WJCC School Board awarded the Partial Demolition of the current James Blair building to Ritchie-Curbow in the amount of $1,106,742.00.

April 12, 2016 – 4th Middle School Update

At their April 12, 2016, Work Session the WJCC School Board discussed the Invitation to Bid for the partial demolition of the current James Blair building.

March 15, 2016 – 4th Middle School Update

At their March 15, 2016, Regular Meeting the WJCC School Board awarded Construction Management Services for James Blair Middle School to MBP in the amount of $558,300.

March 1, 2016 – 4th Middle School Update

At their March 1, 2016, Work Session the WJCC School Board discussed Construction Management Services for James Blair Middle School.

January 19, 2016 – 4th Middle School Update

At their January 19, 2016, Regular Meeting the WJCC School Board received an update on value engineering and preparations for the new middle school.

December 15, 2015 – 4th Middle School Update

At their December 15, 2015, Regular Meeting the WJCC School Board received an update on project milestones and traffic studies for the new middle school.

September 15, 2015 – 4th Middle School Update

At their September 15, 2015, Regular Meeting the WJCC School Board received an update on the new middle school’s proposed site and floor plans. The concept for the school’s instructional wing was also reviewed.

August 18, 2015 – 4th Middle School Update

At their August 18, 2015, Regular Meeting the WJCC School Board received an update on the progress of the New Middle School Conceptual Designs.

April 21, 2015 – 4th Middle School Update

At their April 21, 2015, Regular Meeting the WJCC School Board voted to select Waller Todd Sadler as the firm that will provide Architectural Services for the Design of Middle School Facility.