7/16/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU pointing and patching 
  • Continued window framing and glazing in the research commons and main entrance 
  • Continued installing exterior composite metal panels along the radius wall 
  • Continued hanging and finishing gypsum board in administration and auditeria 
  • Painted the auditeria 
  • Dropped ceiling tile in Unit AB2 
  • Continued rubber floor tile in Unit AB3 and began in Unit AB2 
  • Continued polishing terrazzo flooring in the auditeria 
  • Continued hanging Marlite wood panels in Unit A 
  • Set operable glass partition walls in Units B3, B2, and B1 
  • Continued food service electrical connections 
  • Installed drinking fountains and restroom fixtures in Unit B3 
  • Continued installing ductwork at the stage 
  • Continued controls to the air handling units and programming the mechanical system 
  • Installed pulling data wiring in Units C and D 
  • Placed topsoil on the ball field 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

Terrazzo flooring

6/25/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU pointing and patching 
  • Continued window framing and glazing in the research commons 
  • Continued installing exterior composite metal panels 
  • Continued hanging and finishing gypsum board in administration and auditeria 
  • Applied final coat of paint in Unit AB3 
  • Continued rubber floor tile in Unit AB3 
  • Continued placing and polishing terrazzo flooring 
  • Continued hanging Marlite wood panels in the auditeria and began in Unit A 
  • Continued electrical work in food services 
  • Continued installing ductwork and mechanical pipe in Units C and D 
  • Continued mechanical pipe and controls to the air handling units 
  • Installed equipment racks in the IT closets 
  • Continued fine grading the ball field 
  • Installed the Cooley Field scoreboard 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

6/11/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU pointing and patching 
  • Continued exterior metal sills and interior window trim 
  • Installed glass partition wall track in Unit B 
  • Glass partition panels delivered 
  • Installed operable partition wall track at the stage 
  • Continued hanging exterior composite metal panels in Units A, B, and C 
  • Continued framing interior walls, hanging gypsum board, and finishing in Units A, B, and C 
  • Continued ceiling grid and painting in Units C and D 
  • Interior wood wall panels delivered 
  • Began installing the terrazzo flooring in the commons areas 
  • Continued connecting food service equipment 
  • Continued installing ductwork and mechanical pipe in Units C and D 
  • Continued flushing and filtering the mechanical pipe and testing water quality 
  • Installed the split unit air conditioners in the IT closets 
  • IT closets were inspected for Owner acceptance with punch list distributed to the Contractor 
  • Installed equipment racks in the IT closets 
  • Continued pulling fire alarm wiring in Units C and D 
  • Continued terminating electrical devices in Units A, B, and C 
  • Continued terminating control wiring in the mechanical room and rooftop units 
  • Continued grading the ball field 
  • Removed construction security fencing 
  • Set the structural posts for the Cooley Field scoreboard 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

5/28/2018 – Construction Update

Work Performed this Week:

  • Continued brickwork at the mechanical yard wall and correcting interior masonry items 
  • Installed tube steel for the Gathering Stairs and miscellaneous steel supports for the stage partition wall 
  • Continued glazing the radius windows in Unit A 
  • Installed glass partition wall track in Unit B3 
  • Continued setting exterior frames and doors 
  • Hanging exterior composite metal panels in Units B and A 
  • Continued framing interior walls, hanging gypsum board, and finishing in Units A1 and C 
  • Continued ceiling grid and painting in Units C and D 
  • Continued tilework 
  • Delivered and installed food service equipment 
  • Continued installing ductwork and mechanical pipe in Units C and D 
  • Continued mechanical pipe in the mechanical room and yard 
  • Continued flushing and filtering the mechanical pipe and testing water quality 
  • Installed the split unit air conditioners in the IT closets 
  • Completed electrical connections the mechanical equipment 
  • Continued pulling fire alarm wiring in Units C and D 
  • Continued terminating electrical devices in Units A and B 
  • Continued terminating control wiring in the mechanical room and rooftop units 
  • Continued backfilling the curb and grading the ball field 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

5/21/2018 – Construction Update

Work Performed this Week:

  • Continued exterior framing at the entrance canopies 
  • Continued exterior masonry at the mechanical yard walls 
  • Continued hanging exterior metal panels in Unit B 
  • Continued work on the curtainwalls in Unit B 
  • Continued setting exterior frames, doors, and hardware 
  • Continued interior wall and ceiling framing, gypsum board, and finishing in Units A1, C, and D 
  • Continued ceiling grid in Unit D music 
  • Continued mechanical ductwork in Units A1, C, and D 
  • Continued mechanical pipe in the mechanical room and yard 
  • Continued flushing and filtering the mechanical pipe in preparation for equipment startup 
  • Continued work by all trades in the science classrooms in Units B3 and B2 
  • Continued terminating devices in Units AB3 and AB2 
  • Continued installing lights in AB1 
  • Continued pulling wire in Unit A1 
  • Continued terminating wiring in the main electric room and mechanical room 
  • Continued terminating control wiring in the main mechanical room and rooftop units 
  • The moisture level of the concrete substrate was tested for installation of the flooring systems 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

5/14/2018 – Construction Update

Work Performed this Week:

  • Completed South canopy structural steel 
  • Poured the entrance pad at the South canopy 
  • Continued pointing and patching CMU walls 
  • Continued framing walls, hanging gypsum board, and finishing walls in Unit A1, C, and D 
  • Continued exterior framing at the main entrance canopy 
  • Set exterior door frames 
  • Continued installing exterior composite wall panels in Unit B 
  • Installed pressure bars on the curtainwall in Unit B to permanent secure the glazing 
  • Continued installing windows in Unit D 
  • Continued installing ceiling grid in Unit D music 
  • Installed sprinkler pipe in the fire pump room 
  • Continued flushing and filtering the heating pipe 
  • Started the boilers 
  • Continued welding the chilled water pipes in the mechanical room and yard 
  • Roughed-in walls in the science classrooms 
  • Continued ductwork in food services, Unit D, and Unit A1 
  • Continued pulling cable to the rooftop air handling units and in the mechanical room 
  • Continued trimming out devices in Units A and B 
  • Continued terminating conductor in the main electrical room 
  • Continued installing lights in Units A and B 
  • Continued pulling data cable and trimming out devices in Units A and B 
  • Continued pulling access control wiring to the secured doors in Unit AB1 

 Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

4/30/2018 – Construction Update

Work Performed this Week:

  • Installed structural steel at the South entrance canopy 
  • Continued interior CMU and brick in Units A and C 
  • Continued non-load bearing interior CMU walls throughout 
  • Continued exterior framing and sheathing in Unit A 
  • Installed exterior composite wall panels and flashings in Units A, B, and C 
  • Continued setting windows in Unit A 
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A, B, C, and D 
  • Continued priming and painting in Units B and C 
  • Continued ceramic tile in the food service areas 
  • Continued final hydronic and duct connections to the variable air volume VAVs throughout 
  • Continued hanging variable air volume (VAV) boxes and ductwork throughout 
  • Continued hanging duct in food service 
  • Continued insulating low and medium pressure ductwork and hydronic pipe throughout 
  • Installed flex duct, diffusers, and louvers 
  • Continued setting and welding steel hydronic piping in Unit C mechanical room 
  • Installed lights in the ceiling grid in Units AB3 and AB2 
  • Installed occupancy sensors and other devices in Units A and B 
  • Pulled fire alarm wiring in Units A and B 
  • Continued trimming out electrical work in Units AB3 and AB2 
  • Continued electrical rough-in in the mechanical room and gymnasium 
  • Continued installing ceiling grid in Units AB2 and B1 
  • Continued installing gymnasium equipment 
  • Continued pouring sidewalks in the East parking lot 
  • Poured the concrete pad at the bus fuel tank 
  • Continued pulling data wiring in Unit B1 
  • The generators were delivered and set on the equipment pads in the mechanical yard 
  • The projector screens were delivered 
  • Relocated the field office trailers for resuming site work 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

4/23/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU and brick in Units A and C 
  • Continued non-load bearing interior CMU walls throughout
  • Continued exterior framing and sheathing in Unit A 
  • Installed exterior composite wall panels and flashings in Units A, B, and C 
  • Continued setting windows in Unit A 
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A, B, and C 
  • Continued priming and painting in Units B and C 
  • Completed ceramic tile in the locker rooms and food service areas 
  • Continued final hydronic and duct connections to the variable air volume VAVs throughout 
  • Set the cooling towers on the support framing in the mechanical yard 
  • Continued hanging variable air volume (VAV) boxes and ductwork in Units A, C, and D 
  • Continued hanging duct in food service 
  • Continued insulating low and medium pressure ductwork and hydronic pipe in Units A, B, and C 
  • Continued setting and welding steel hydronic piping in Unit C mechanical room 
  • Installed lights in the ceiling grid in Units AB3 and AB2 
  • Installed occupancy sensors in Units A and B 
  • Pulled fire alarm wiring in Units A and B 
  • Continued trimming out electrical work in Units AB3 and AB2 
  • Continued electrical rough-in in the mechanical room and gymnasium 
  • Continued installing ceiling grid in Units AB2 and B1 
  • Permanent power connected and meter set 
  • Permanent service line connected and meter set 
  • Began installing science lab casework 
  • Began installing gymnasium equipment 
  • Installed the cooler and freezer in food service 
  • Sitework resumed with sidewalks poured in the East parking lot 
  • Bus fuel tank pad formed and ready for the concrete 
  • Continued pulling data wiring in Unit B1 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

4/9/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU and brick in Units A and C
  • Continued non-load bearing interior CMU walls throughout
  • Continued exterior framing and sheathing in Unit A
  • Installed exterior composite wall panels and flashings in Units A, B, and C
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A and B
  • Continued priming and painting in Units B and C
  • Set ceramic tile in the locker rooms
  • Continued final hydronic and duct connections to the VAVs throughout
  • Continued hanging variable air volume (VAV) boxes and ductwork in Units A, C, and D
  • Hung duct in Food Service
  • Continued insulating low and medium pressure ductwork and hydronic pipe in Units A and B
  • Continued setting and welding steel hydronic piping in Unit C mechanical room
  • Installed lights in the ceiling grid in Units AB3 and AB2
  • Installed occupancy sensors in Units A and B
  • Pulled fire alarm wiring in Units A and B
  • Continued electrical rough-in in the mechanical room and gymnasium
  • Continued installing ceiling grid in Units AB2 and B1
  • Completed underground rough-in for the fuel pump
  • Set the new transformer and terminated conductor in the switchgear and new transformer
  • Set the electrical meter
  • Outage effecting the Central Office is scheduled between 5:00 am and 6:30 am on Monday, April 9, 2018 to make the final connection at the existing transformer and energize the new building
  • Set the gas meter

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

4/2/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU and brick in Units A and C
  • Continued non-load bearing interior CMU walls in throughout
  • Continued exterior framing and sheathing in Unit A
  • Continued installing windows and curtainwall
  • Installed exterior composite wall panels and flashings in Units A and C
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A
    and B
  • Continued priming and painting in Units B and C
  • Set ceramic tile in the locker rooms
  • Continued final hydronic and duct connections to the VAVs in Units A and B
  • Continued hanging variable air volume (VAV) boxes and ductwork in Units A, C, and D
  • Continued insulating low and medium pressure ductwork in Units A and B
  • Continued setting and welding steel hydronic piping in Unit C mechanical room
  • Installed lights in the ceiling grid in Units AB3 and AB2
  • Pulled fire alarm wiring in Units A and B
  • Roughed-in electrical in the mechanical room
  • Continued installing ceiling grid in Unit AB2
  • Installed the range hoods
  • Installed the fuel tank for the buses
  • Pulled the underground conductor for permanent power

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.